Essential gas main replacement Broomfield, Henfield

From Monday 19 June SGN contractor DJ Utilities will commence a programme of work to replace gas mains in your local area. This essential work will involve replacing the old metal gas pipes with new plastic pipes to ensure we can continue to provide residents and community with a safe and efficient gas supply.

Due to the location of the gas main in the road, varying traffic management will be required, the following outlines the planned programme.

Please note these dates are for guidance and may vary as they are subject to progress and access.

Road Closure required

Lower Station Road - 19 June (duration 1 week)

Lower Station Rd to the junction of Batts Pond Lane – the road closure is planned for one week.

Road Closure required

Nep Town Road - 26 June (duration 15 weeks)

The team will be working their way along Nep Town Road taking the closure with them as they progress, vehicle access to properties will change as the closure moves. Hewitts and Blackgate Lane will be completed as the team progresses past on Nep Town Road. Resident vehicle access to Hewitts and Blackgate Lane will be via the Nep Road closure diversion.

Vehicle access arrangements for the closures

There will be no through vehicle access past the point of closure in both directions, local diversion routes will be in place.

Vehicle access to properties within closures will be maintained wherever possible – our team will keep residents informed of the local arrangement. Pedestrian and cycle access will be maintained at all times.

Bus route will be on diversion – we would advise bus passengers to speak to their bus provider for more information about changes to bus routes, timetables and bus stop locations.

The following three roads are still being planned, we’ll confirm exact dates as soon as they are confirmed. Road closures will not be required to complete the work on these roads.

Broomfield Road and Croft Lane – September start date TBC (duration 6 weeks)

Lovers Walk (Footpath Closure) / Cagefoot Lane (Private Rd ) – October start date TBC (duration 6 weeks)

Mill Drive / Cedar Way- December start date to be confirmed

If you’d like to get in touch with SGN about these works, you can speak to our Customer Service team on 0800 912 1700 who will direct your enquiry to a member of the project team for a response.

We appreciate the nature of our work can be disruptive, our engineers will be doing all they can to minimise this wherever possible. Thank you for your patience and understanding.

The SGN Project Team

 

 

 

 
Who we are

WHO WE ARE

Find out more about your Parish Councillors and the Parish Office Team

READ MORE
 
How we work

HOW WE WORK

Find the Parish Council Policies and Henfield Parish Council's Public Open Data

READ MORE
 
Our responsibilities

OUR RESPONSIBILITIES

Find out about the role of the Parish Council and the other Local Authorities, Horsham District Council and West Sussex County Council

READ MORE